Commercial heat pump requirements in New Zealand changed on 1 May 2026, with new energy efficiency requirements introduced for certain larger air-conditioning and heat pump systems.
The changes extend Minimum Energy Performance Standards (MEPS) to certain systems above 65 kW — equipment commonly used in larger commercial and industrial applications.
For businesses considering a move away from traditional boiler systems, modern commercial heat pump systems can provide an efficient alternative for a range of heating applications.
So, what has changed, and what does it mean when considering a new commercial heating system?
What changed on 1 May 2026?
New Zealand’s Energy Efficiency (Energy Using Products) Regulations have been updated to include certain air conditioners and heat pumps above 65 kW.
Previously, this category of larger equipment was not covered by the same Minimum Energy Performance Standards.
From 1 May 2026, affected equipment manufactured in New Zealand or imported into New Zealand must:
- Meet the applicable Minimum Energy Performance Standards (MEPS)
- Be tested in accordance with the relevant standards
- Be registered before it can be supplied in New Zealand
The changes bring New Zealand’s requirements more closely into line with Australian energy efficiency requirements.
What are Minimum Energy Performance Standards?
Minimum Energy Performance Standards, commonly known as MEPS, set a minimum level of energy efficiency that regulated equipment must achieve.
For larger air-conditioning and heat pump systems covered by the new requirements, performance is assessed using measures including:
- AEER – Annual Energy Efficiency Ratio for cooling performance
- ACOP – Annual Coefficient of Performance for heating performance
Put simply, the regulations are designed to prevent inefficient equipment from entering the New Zealand market and to provide a consistent minimum standard for energy performance.
Which commercial heat pumps are affected?
The new requirements generally apply to air-conditioning and heat pump equipment that:
- Uses a vapour-compression cycle
- Is air-to-air
- Has a cooling capacity greater than 65 kW, or a heating capacity greater than 65 kW for heating-only products
- Is single-phase or three-phase
- Can be ducted or non-ducted
- Is unitary, single-split, or multi-split equipment
Not all commercial heat pump technologies meet these particular requirements. Some equipment types, including water-to-air systems and liquid-chilling packages, are excluded.
Because commercial heating systems can use a range of technologies and configurations, it is important to confirm which requirements apply to the particular equipment being considered.
What about equipment imported before 1 May 2026?
There are transitional provisions for existing equipment.
Air conditioners and heat pumps above 65 kW that were manufactured in New Zealand or imported before 1 May 2026 can continue to be supplied without meeting the new requirements.
Equipment manufactured locally or imported from 1 May 2026 onwards, where it falls within the regulated product classes, must comply with the new requirements before it can be supplied.
What does this mean for commercial projects?
For building owners, consultants, and contractors, the changes add another consideration when specifying new commercial heating and cooling equipment.
When planning a new system or replacing an existing plant, it is worth considering not only the initial equipment cost, but also:
- Energy efficiency
- Operating temperatures
- Heating and cooling demand
- System sizing
- Expected operating hours
- Integration with existing plant
- Refrigerant selection
- Controls and monitoring
- Future maintenance requirements
- Compliance with current New Zealand requirements
Correct system selection and design remain particularly important. A highly efficient piece of equipment still needs to be correctly sized, integrated, and controlled to achieve good real-world performance.
Commercial heating is continuing to evolve
Commercial heating technology is changing rapidly, with heat pumps increasingly being considered alongside traditional boiler systems for space heating, process heating and hot water applications.
Higher-temperature heat pumps, improved controls and alternative refrigerants are expanding the range of applications where heat pump technology can be considered.
At the same time, regulatory changes such as the new requirements for larger systems are placing greater emphasis on measurable energy performance.
Planning a commercial heating or hot water project?
Flow Energy works with commercial and industrial clients to develop heating and hot water solutions tailored to each project’s requirements.
From heat pump and boiler systems through to prefabricated plant solutions, controls and system integration, our focus is on selecting practical, efficient equipment and designing it to work effectively as part of the complete system.
Planning a commercial heating upgrade or new project? Contact Flow Energy to discuss the options available for your application.